Contraction marks

First, the injection characteristics of the surface defects often associated with marks, but also to the surface of the plastic from the mold shrinkage from the formation.

 Second, the reasons for problems that may occur

(1) The melting temperature is not too high or too low.
(2) Insufficient mold cavity plastic.
(3) When the cooling phase the contact surface of the plastic to overheat.
(4) Runners unreasonable, gate-section is too small.
(5) The die temperature is adapted to the characteristics of the plastic.
(6) The product structure is irrational (strengthened into ancient too high, too thick, obviously varying thickness).
(7) The cooling effect is good, continue to shrink after product release.

Third, the remedies

(1) Adjust the plunger cylinder temperature.
(2) The adjustment screw speed to obtain the correct screw surface speed.
(3) Increase the amount of injection. (
4) ensure the use of proper litter; increase screw forward time; increased injection pressure; increase injection speed.
(5) Check the stop valve is installed correctly, because the non-normal operation will lead to pressure loss.
(6) Reduce the mold surface temperature.
(7) Correction runner to avoid excessive pressure loss; according to actual needs, and expand the cross-sectional dimensions.
(8) The appropriate mold temperature control depending on the characteristics of the plastic and the product structure.
(9). Improve the product structure in the permit.
(10) Try to make the product has adequate cooling

Warpage of plastic parts

First, the characteristics of injection molded parts defects similar to the shape of the mold cavity is a twisted version but the shape of the mold cavity
Second, the reasons for problems that may occur

(1). Bend because there are too many internal stress within the injection molded parts.
(2) mold filling speed.
(3) Insufficient mold cavity plastic.
(4) plastic temperature is too low or inconsistent.
(5) at the top of injection molded parts too hot out.
(6). Cooling inadequate or move, scheduled to die temperature is inconsistent.
(7). Injection irrational structure (such as ribs concentrated on one side, but far away).

Third, the remedies

(1) Reduce the injection pressure.
(2) Reduce the screw forward time.
(3) Increase the cycle time (especially cooling time). From the mold after (especially thick injection molded parts) top out immediately immersed in warm water (38oC) makes injection molded parts to cool slowly. (4) Increase the injection speed.
(5) Increasing the temperature of the plastic.
(6) cooling equipment.
(7) appropriate to increase or improve the cooling conditions of the cooling time, as far as possible to ensure dynamic and stationary die mold temperature consistent.
(8) In accordance with the actual situation of improving the structure of plastic parts in the permit. Plastic injection filling defect characteristics dissatisfied injection molding process is not complete, because the cavity does not fill plastic injection molding process or lack of certain details.

Second, the reasons for problems that may occur
(1) Insufficient injection speed.
(2). Shortage of plastic.
(3) The screw at the end of the trip did not leave a screw litter.
(4) Changes in operating time.
(5). Plunger cylinder temperature is too low.
(6) lack of injection pressure.
(7) Nozzle partially blocked.
(8) or plunger nozzle heater does not work outside the cylinder.
(9). Injection time is too short.
(10) plastic hose attached to the hopper wall.
(11). Injection molding machine capacity is too small (ie, weight or plasticizing injection capacity).
(12) The mold temperature is too low.
(13) There is no clean up mold of anti-rust oil.
(14). Retaining ring is damaged, there is melt back phenomenon.

Third, the remedies

(1) Increase the injection speed.
(2) checks the amount of plastic in the hopper.
(3) Check whether the correct set of injection stroke, needed to be changed.
(4) Check the check valve wear or cracks.
(5) Check the operation is stable.
(6) Increase melt temperature.
(7) Increased back pressure.
(8) Increase the injection speed.
(9) Check the nozzle hole there is no foreign body or plasticizing plastics.
(10) Check all heaters outer layer ammeter test energy output is correct.
(11) Increase screw forward time.
(12). Increased cooling capacity hopper throat area, or lower the temperature after the plunger cylinder area.
(13). Using large injection molding machine.
(14) The appropriate mold temperature rises.
(15). Cleaned rust clean the mold.

(16). Inspection or replacement.